Monday, 23 March 2015

More of the same.

More progress over the last week.
Lots more bricks have been laid and the issues that were highlighted with the frame appear to have mostly been resolved over the last week.
Doors appear to have been fitted and the heating/aircon system install has also started, along with the bathroom fit-outs.

Bricks;




Doors, bathrooms and heating system;










Resolved frame issues;







New issues;

Front door has the wrong glass type fitted.

heating/aircon frame in the master bedroom has tripled in size for some reason since my last visit. The older/smaller portion of the frame closer to the window is what's on the plans. Need to raise this.



Tuesday, 10 March 2015

More bricking

More bricking has gone up since the last visit. The garage has also now been started. It's going to look huge once the garage roof has been finished.