Friday 25 September 2015

Things are improving.

Went up to site this morning to meet the site supervisor and see the rectification of the items I was unhappy with from the last visit and getting the group building manager involved.

I'm happy to say that after re-working the eaves a 5th time, they are now straight at last.

Insulation has also been reworked and looks a lot tidier and the damaged window on the games room had already been removed in anticipation of the replacement being fitted this afternoon.










Looks like we've had the render applied to the front of the house as well.

There's still a few items outstanding to complete the lockup stage (replace ensuite window and replace the metal capping on the theatre room projections - as well as adding splits to fill the gaps in the capping), but once these are done things should move forward quite quickly.

Plaster is scheduled to start next week as well as the scaffolding coming down and then knocking down the garage and rebuilding with the new bricks so that everything matches colour wise.

Getting the group building manager involved again has had another positive effect on the build. I just hope that things don't slip again once we get past the external.

Much happier :)



No comments:

Post a Comment